But the company owned by C. C. Myers, a 6-foot-5 contractor who favors peacock cowboy boots, fixed the mangled freeway so fast that some residents have recalibrated their respect for the California Department of Transportation, which hired him.

The state estimated that repairs to the 165-foot-long ramp between Interstates 80 and 580 would take 50 days and cost $5.2 million. For every day short of the June 26 deadline, it promised a $200,000 bonus, not to exceed a total of $5 million. The highest bid came in at $6.4 million. Mr. Myers’s company, C. C. Myers Inc., won with the lowest bid — $867,075 — and completed the project in 17 days, winning the full $5 million.